  • North Fork Montour Run
    No
    Underground
    Passive Treatment System
    Montour Run
    Clinton
    North Fork Montour Run

    A passive system was installed to treat an underground mine discharge which was impacting the North Fork of Montour Run. The project incorporated the use of 3 ponds built by the PA Turnpike Commission during construction of the Findlay Connector

    2008
    $674,314.00
    $0.00
Water Quality Data Summary
Sample PointFlow - Field!!(gal/min)pH - Field!!(S.U.)pH - Lab!!(S.U.)ORP - Field!!(mvolts)DO - Field!!(mg/L)Temp - Field!!(C)Cond - Lab!!(umhos/cm)Alkalinity - Field!!(mg/L)Alkalinity - Lab!!(mg/L)Acidity - Lab!!(mg/L)T. Fe  - Lab!!(mg/L)D. Fe - Lab!!(mg/L)T. Mn  - Lab!!(mg/L)D. Mn  - Lab!!(mg/L)T. Al - Lab!!(mg/L)D. Al - Lab!!(mg/L)SO4 - Lab!!(mg/L)TSS - Lab!!(mg/L)
FCRAW46.55.695.2934.61.2613.61871112.5752.3874.43156.26154.747.047.115.361.34932.939.6
NFWL447.277.3126.83.2620.51760143.29144.95-116.251.590.855.136.640.130.05652.215.6
Treatment Technologies