  • Coal Run Site No. 8
    No
    Underground
    Passive Treatment System
    Schrader Creek
    Leroy
    Coal Run

    Brought online Nov. 24, 2010. The project uses a system of pipes to divert most of the stream through three concrete tanks embedded in the ground, each containing 100 tons of limestone rock.

    2010
    $151,785.00
    $0.00
Treatment Technologies
Treatment Technology Quantity of Elements
Up Flow Limestone Bed 3