Project Details
  • Brandy Camp
    No
    Surface
    Active Treatment System
    Little Toby Creek
    Brandy Camp
    Brandy Camp Creek

    This site may have been strictly a passive system and then converted to a hybrid system that consisted of a hydrated lime silo followed by settling ponds and wetlands. An Active Chemical Water Treatment plant has since replaced the original treatment system and is operated by PA DEP that includes 2 sets of clarifiers, 2 mix tanks, 2 aeration tanks, large filter press, sludge holding tanks, and a lime silo

    2001
    $2,590,360.00
    $778,776.00
Water Quality Data Summary
Sample PointFlow - Field!!(gal/min)pH - Field!!(S.U.)pH - Lab!!(S.U.)ORP - Field!!(mvolts)DO - Field!!(mg/L)Temp - Field!!(C)Cond - Lab!!(umhos/cm)Alkalinity - Field!!(mg/L)Alkalinity - Lab!!(mg/L)Acidity - Lab!!(mg/L)T. Fe  - Lab!!(mg/L)D. Fe - Lab!!(mg/L)T. Mn  - Lab!!(mg/L)D. Mn  - Lab!!(mg/L)T. Al - Lab!!(mg/L)D. Al - Lab!!(mg/L)SO4 - Lab!!(mg/L)TSS - Lab!!(mg/L)
D1531.74.67.04------1536--70.41-5.0725.15--3.84--4.52--873.28
BCA286.34.775.15------1501--33.1118.758.4739.138.458.645.243.3191349.1
BCE0--9.3------1608--20.2-3211.1--1.46--1.8--911.452
BCF0--9------1612--20.88.80.2--0.12--0.2--932.416
Treatment Technologies
Treatment Technology Quantity of Elements
Settling Pond 2